Building Completed
Site preperation work began on Monday December 10th, 2007. The ground breaking ceremony with the Chamber of Commerce was Tuesday December 18th, 2007 at 10:00 a.m. Ceco Building arrived at site on January 2nd, 2008. The main structure was in place January 13th, 2008. The walls went up on January 28th, 2008. The roof was finished on Febuary 10th, 2008. The interior was laid out on Febuary 27th, 2008. The front windows were put in on March 2nd, 2008. The doors were put in on March 22nd 2008. The building is complete. Please come visit us at 825 North Henderson Street.
|